# Execution Controls Implementation Plan
|
||||
|
||||
## Objective And Sprint Scope
|
||||
|
||||
Implement the accepted target in [execution-controls.md](execution-controls.md)
|
||||
from the v0.22.0 execution architecture. The feature roadmap owns intent and the
|
||||
four accepted lifecycle decisions; this document selects the API and the work
|
||||
needed to implement them. [Audita's request](audita-request.md) supplies the
|
||||
consumer scenarios.
|
||||
|
||||
Work through Stage 1 through Stage 8 in order. Each stage is scoped for one Luna
|
||||
coding-agent prompt. This is one end-to-end sprint: intermediate stages may
|
||||
temporarily fail to compile or leave wiring incomplete. Do not build temporary
|
||||
compatibility layers merely to make intermediate commits green. There are no
|
||||
intermediate human-review or external-publication gates. Completion requires
|
||||
the assembled feature and its validation, not just completion of individual
|
||||
stages.
|
||||
|
||||
Read [development.md](../development.md), the [agent policy](../policy/agents.md),
|
||||
and the applicable architecture, testing, and documentation policies before
|
||||
work. Preserve unrelated changes. Follow the existing commit policy for finished
|
||||
units; report intermediate validation honestly. This plan authorizes no release,
|
||||
push, dependency update, configuration-format change, or new consumer workflow
|
||||
beyond the execution controls described here.
|
||||
|
||||
## Selected API And Semantics
|
||||
|
||||
Add these fields to the existing public `RunRequest`, without introducing an
|
||||
execution-options object, coordinator executor, or general hook framework:
|
||||
|
||||
```go
|
||||
OperationTimeout time.Duration `json:"-" yaml:"-"`
|
||||
OnPrepared func(context.Context, PreparedRun) `json:"-" yaml:"-"`
|
||||
```
|
||||
|
||||
Add one public sentinel, alongside the current execution errors:
|
||||
|
||||
```go
|
||||
var ErrOperationTimeout = errors.New("operation timeout exceeded")
|
||||
```
|
||||
|
||||
The spelling of an error message is not a contract. No exported timeout error
|
||||
type, new observer event, or new failure-category enum is needed.
|
||||
|
||||
### Entry-Point Contract
|
||||
|
||||
| Entry point | OperationTimeout | OnPrepared |
|
||||
| --- | --- | --- |
|
||||
| `Run` | A positive value starts a fresh child budget before preparation, covering preparation and execution. | Notify once if execution reaches the prepared point before first generation. |
|
||||
| `Coordinate` | Each returned request receives ordinary `Run` semantics with a fresh scope. | Ordinary per-request notification; no coordinator-specific copy of the option. |
|
||||
| `PrepareExecution` | Retain the value privately, without starting a timer. Preparation uses its supplied context. | Retain the selected function privately without invoking it. |
|
||||
| `RunPrepared` | Start the retained positive duration after the successful claim, before execution callbacks, credential revalidation, and admission. | Notify once when the claimed execution reaches the prepared point. |
|
||||
| `Prepare`, `ValidateRequest` | Do not start a timer; use the supplied context as today. | Do not invoke or retain the notification. |
|
||||
| `PreparedExecution.Details`, `Discard` | Do not start a timer. | Do not invoke the notification. Discard drops its retained reference. |
|
||||
|
||||
- A positive duration opts in. Zero and negative durations select no additional
|
||||
timeout. This follows a nonpositive-means-unselected convention, avoids a new
|
||||
request rejection rule, and leaves the parent deadline effective. There is no
|
||||
default operation duration, upper bound, profile setting, or engine setting.
|
||||
- The provider's existing generation timeout remains independent. Do not copy
|
||||
`OperationTimeout` into `ExecutionTarget`, provider JSON, or prepared/result
|
||||
metadata. Neither control changes prompt hashes or configuration inspection.
|
||||
- The budget is continuous across preparation, capacity waiting, notification,
|
||||
generation, transient retries/backoff, validation, and structural repair. It
|
||||
is not restarted between phases, attempts, or repair generations.
|
||||
- Split preparation retains a duration, not a context, deadline, timer, or
|
||||
cancel function. Idle time does not count. A shared caller-created deadline
|
||||
remains the way to bound preparation and later execution together.
|
||||
- A nil notification selects no diagnostic copying. A selected function receives
|
||||
the operation context and a detached, credential-redacted `PreparedRun` value
|
||||
representing the logical request. Its nested mutable values belong to the
|
||||
application. Reuse the existing projection used by `Details()`.
|
||||
- Notification is synchronous, has no error return, and runs after successful
|
||||
preparation and admission, before the first generation. Logical admission is
|
||||
still held. Its time consumes the selected operation budget. It may retain
|
||||
details for later diagnostics; PromptKit does not own writes or write errors.
|
||||
- Check context before notification and again before generation after it
|
||||
returns. A callback may block or ignore context; do not introduce a goroutine
|
||||
to interrupt it. Callback panic propagates after deferred resource cleanup,
|
||||
without a new terminal-event guarantee.
|
||||
- Callback selection is copied as a function value, not as a deep copy of its
|
||||
closure. Shared callback state is application-synchronized; separate runs can
|
||||
invoke a common callback concurrently. Later reassignment of the original
|
||||
request field cannot replace a prepared handle's retained function.
|
||||
- Notification is conditional on reaching that execution point. Admission or
|
||||
preparation failure can prevent it. Do not render again, reorder admission,
|
||||
or promise a diagnostic snapshot for every failed operation. Split callers
|
||||
can still inspect a successfully prepared handle through `Details()`.
|
||||
|
||||
### Timeout Attribution And Completion
|
||||
|
||||
Use the standard library's `context.WithTimeoutCause` with a distinct cause
|
||||
value for each selected scope. Record the scope's own cause identity so an
|
||||
inherited timeout from an enclosing operation cannot be mistaken for this
|
||||
invocation's timer. Do not classify by error text or by `DeadlineExceeded`
|
||||
alone. No strict ordering of independently racing cancellations is promised.
|
||||
|
||||
When an execution fails through its context deadline and the child context's
|
||||
recorded cause is this scope's own timer cause, return an error matching both
|
||||
`ErrOperationTimeout` and `context.DeadlineExceeded`. Preserve existing operation
|
||||
and collaborator error identities. An earlier parent deadline/cancellation or
|
||||
a provider deadline must not acquire the local marker merely because it is a
|
||||
deadline error. An unrelated failure must not acquire it merely because the
|
||||
timer has also expired. Parent-provided error causes, if any, retain their
|
||||
existing behavior; this feature need not reinterpret them.
|
||||
|
||||
Finalize attribution from the operation's returned error before canceling its
|
||||
child scope and before terminal observer delivery. A nil execution error remains
|
||||
a completed result, including a completed structural rejection. Do not add a
|
||||
post-terminal `ctx.Err()` check that converts it into an error. Slow terminal
|
||||
observers and deferred context cleanup cannot change the chosen outcome. This
|
||||
does not strengthen cancellation into forced interruption or a guarantee that
|
||||
every context-ignoring collaborator will return by the deadline.
|
||||
|
||||
The terminal event continues using the existing deadline failure category for
|
||||
a timeout error. Groups continue aggregating those ordinary terminal facts.
|
||||
The child scope is cleaned up before `Run`/`RunPrepared` returns to the next-turn
|
||||
callback; that callback receives the coordinator parent context, not the child.
|
||||
Existing parent cancellation and undelivered-result rules remain unchanged.
|
||||
|
||||
## Implementation Map
|
||||
|
||||
Use existing owners rather than adding a new public package:
|
||||
|
||||
- Public declarations and contract: [types.go](../../types.go),
|
||||
[engine.go](../../engine.go), and [prepared_execution.go](../../prepared_execution.go).
|
||||
- Public conversion and error projection: [convert.go](../../convert.go),
|
||||
[errors.go](../../errors.go), and [observations.go](../../observations.go).
|
||||
- Internal request values: [domain.go](../../internal/domain/domain.go).
|
||||
- Timeout lifecycle and notification orchestration: `internal/usecase`, chiefly
|
||||
[runner.go](../../internal/usecase/runner.go) and
|
||||
[prepared_execution.go](../../internal/usecase/prepared_execution.go).
|
||||
- Existing private operation-error representation:
|
||||
[operation_error.go](../../internal/usecase/operation_error.go).
|
||||
- Ordinary coordinator integration: [coordinate.go](../../coordinate.go) and
|
||||
[internal coordinator](../../internal/usecase/coordinate.go).
|
||||
|
||||
The root remains a facade. Keep timer construction and cause-attribution logic
|
||||
in a small internal helper; the facade may establish that scope and project its
|
||||
errors while managing its existing observation lifecycle. Internal packages must
|
||||
not import the root package or depend on the public `PreparedRun` representation.
|
||||
Private helper names and equivalent internal organization may change; the
|
||||
selected public behavior and ownership boundaries are what matter.
|
||||
|
||||
## Stage 1: Add The Request Contract And Conversion
|
||||
|
||||
Outcome: the selected API and internal request plumbing exist, ready for the
|
||||
execution stages to consume.
|
||||
|
||||
1. Add `OperationTimeout`, `OnPrepared`, and `ErrOperationTimeout` to the public
|
||||
declarations above. Write their GoDoc from the entry-point and ownership
|
||||
contract in this plan, explicitly separating operation and provider timeouts.
|
||||
2. Extend `domain.RunRequest` with the duration and an internal callback of shape
|
||||
`func(context.Context, *domain.PreparedRun)`. Document the callback argument
|
||||
as borrowed read-only internal state. It is not a public mutable snapshot.
|
||||
3. Extend `toDomainRunRequest` to copy the duration and capture the selected
|
||||
public callback function in a local variable. Only when it is non-nil, adapt
|
||||
it by projecting the supplied prepared state through `fromDomainPreparedRun`
|
||||
and passing the resulting value. This projection is the public ownership
|
||||
boundary; do not deep-copy the domain snapshot first as well.
|
||||
4. Keep these fields out of public prepared/result JSON and opaque handle
|
||||
details. Request conversion does not start a timer, invoke a callback, or
|
||||
reject an execution-only control on preparation-only entry points.
|
||||
5. Add the private timeout error identity in `internal/usecase`, using the same
|
||||
existing separation between internal and public sentinels. Add its public
|
||||
projection to `errors.go` when introducing the attribution wrapper in Stage 2.
|
||||
|
||||
Validation: focused conversion tests should establish option forwarding and
|
||||
conditional adaptation. Reuse existing nested-value projection tests instead of
|
||||
retesting every existing `PreparedRun` field. Compilation may remain incomplete
|
||||
until the execution wiring lands; do not claim the feature works at this stage.
|
||||
|
||||
## Stage 2: Bound Ordinary Execution And Preserve Its Error Outcome
|
||||
|
||||
Outcome: `Engine.Run` owns one continuous optional budget and returns the same
|
||||
failure classification it publishes to observers.
|
||||
|
||||
1. Add a small internal operation-scope helper using `WithTimeoutCause`. For
|
||||
nonpositive durations, reuse the parent context without a timer. For positive
|
||||
durations, retain a fresh per-invocation cause token and a cancel function.
|
||||
Use a real distinct identity, not a shared sentinel or zero-sized token whose
|
||||
pointer identity cannot distinguish scopes.
|
||||
2. Give the helper an error-finalization operation: for a non-nil returned error,
|
||||
require both a match to the operation context's deadline error and equality
|
||||
of its recorded cause with this scope's token before adding the private
|
||||
timeout identity. Leave nil errors and unrelated errors unchanged. Preserve
|
||||
the original error as a cause.
|
||||
3. Reuse `usecase.OperationError` with the private timeout category to carry the
|
||||
marker around the existing error, rather than creating a public error
|
||||
hierarchy. Project that category to `ErrOperationTimeout` through the
|
||||
existing `publicOperationError` machinery. Keep the original phase category
|
||||
and context cause inspectable through the nested chain.
|
||||
4. Establish the ordinary scope in the facade's `Run` entry, after masking
|
||||
inherited execution-observation state and before start-event delivery and
|
||||
request preparation. Both observed and unobserved runs use it. Pass its
|
||||
context through request conversion, internal engine delegation, admission,
|
||||
preparation, and all generation/validation work. Do not also start a second
|
||||
timer inside `Runner.Run`.
|
||||
5. Adjust the private facade `run` path as needed to finalize the execution
|
||||
error before applying public error projection once. On normal return, freeze
|
||||
attribution and the returned result/error, clean up the child, then classify
|
||||
and deliver the existing terminal event. Preserve normal observation of
|
||||
request conversion and preparation failures. Handle all early returns; install
|
||||
cleanup before any user callback can panic.
|
||||
6. Do not change provider timeouts, retry eligibility, repair limits, scheduling,
|
||||
or existing result timing conventions to implement this feature. A timer
|
||||
expiring while terminal observation runs is not another execution failure.
|
||||
|
||||
Validation: narrow helper tests cover disabled scopes, local expiry, parent
|
||||
deadline/cancellation, inherited operation causes, unrelated errors, and nil
|
||||
completion. Add public `Run` tests proving the marker survives phase wrapping
|
||||
and agrees with an ordinary deadline terminal event. Provider-only deadline
|
||||
errors while the operation child is active must not gain the marker.
|
||||
|
||||
## Stage 3: Retain Controls Across Split Preparation
|
||||
|
||||
Outcome: prepared execution carries the selected duration and notification,
|
||||
without keeping a live operation scope while idle.
|
||||
|
||||
1. Extend `preparedExecutionPayload` with the duration and internal notification.
|
||||
`PrepareExecution` copies them from the converted request only after its
|
||||
ordinary successful preparation. Preparation itself uses its supplied
|
||||
context, without starting the selected timer or calling the notification.
|
||||
2. Extend payload clearing for both fields. Preserve the existing atomic claim,
|
||||
owner checks, foreign/reused-handle behavior, and durable redacted details.
|
||||
A discard or completed/unwound claim drops PromptKit's callback reference.
|
||||
3. After a successful `Runner.RunPrepared` claim, establish the scope with the
|
||||
retained duration, before the retained observer's start delivery, credential
|
||||
revalidation, and admission. Defer payload and scope cleanup before callback
|
||||
work. A failed claim neither starts notification nor changes existing silent
|
||||
invalid-handle behavior.
|
||||
4. Pass the child through execution and finalize the returned error with the
|
||||
same helper before cleanup and facade terminal classification. Keep this
|
||||
lifecycle in the internal prepared runner rather than borrowing duration or
|
||||
callback state from an unclaimed handle in the facade.
|
||||
5. `RunPrepared`'s facade projects the resulting error and emits its one existing
|
||||
terminal event after resource release. Do not reapply the timer at the facade
|
||||
or retain the preparation context. Namespace views keep their shared-owner
|
||||
behavior and use the handle's original selections.
|
||||
|
||||
Validation: extend prepared-execution coverage to show that preparation and an
|
||||
idle delay longer than the selected duration do not consume its execution
|
||||
budget; later execution does. Reassignment of the original request does not
|
||||
change the retained duration/callback. Cover earlier caller deadlines and a
|
||||
shared caller deadline across preparation and execution. Existing claim-race,
|
||||
discard, foreign-owner, credential, and error-identity tests remain applicable.
|
||||
Notification invocation itself is completed in Stage 4.
|
||||
|
||||
## Stage 4: Notify From The Actual Shared Prepared Snapshot
|
||||
|
||||
Outcome: ordinary and prepared execution expose one detached logical request
|
||||
before first generation, without repeating preparation.
|
||||
|
||||
1. Thread the internal notification from `Runner.Run` and the claimed payload
|
||||
into the existing shared `executePreparedRun` entry. At that entry, preparation
|
||||
is complete and logical admission is held on both paths.
|
||||
2. When selected, check the operation context, invoke the internal adapter with
|
||||
the actual retained prepared state, and check context again before entering
|
||||
generation. A context failure at this boundary follows the existing
|
||||
generation operation-error wrapping, preserving context identity and gaining
|
||||
local-timeout identity only through the scope finalizer.
|
||||
3. Invoke once per executing logical request, not per transport retry or repair.
|
||||
Do not call `Prepare`, `Details`, artifact readers, renderers, or schema
|
||||
preparation again to produce the notification. With nil `OnPrepared`, avoid
|
||||
constructing a public details copy.
|
||||
4. Keep the prepared state's API key redacted. Generation still receives its
|
||||
private direct credential through the existing separate path. Preserve the
|
||||
complete assembled messages, schema, settings, input hashes, session,
|
||||
ancestry, and preparation metadata in the delivered public value.
|
||||
5. Leave logical admission held; do not release/reacquire it around notification.
|
||||
Invoke application code without holding the handle mutex or a capacity
|
||||
manager lock. Preserve panic propagation while defers release the lease,
|
||||
timer, and claimed payload. A panic does not make a handle reusable.
|
||||
|
||||
Validation: one ordinary and one split public test establish ordering before
|
||||
generation and exact callback selection. Add focused context-before/after
|
||||
notification tests and an internal cleanup regression if the public capacity
|
||||
probe alone cannot demonstrate payload cleanup. More extensive ownership and
|
||||
failure assertions belong to Stage 6, not duplicate tests here.
|
||||
|
||||
## Stage 5: Verify Continuous Budgets Across Execution Phases
|
||||
|
||||
Outcome: tests demonstrate that one scope reaches all relevant collaborators,
|
||||
with correct attribution and observation on failure.
|
||||
|
||||
1. Add focused tests for preparation expiry through a context-aware injected
|
||||
artifact reader, generation-capacity waiting on a real limited backend,
|
||||
interrupted built-in retry backoff, and structural repair expiry. Verify
|
||||
standard context matching, local marker, and retained phase identity where
|
||||
that phase already supplies one. Cover ordinary and split paths without
|
||||
mechanically duplicating every case on both.
|
||||
2. Use a narrow internal runner test for validation-phase expiry, since validation
|
||||
collaborators are not a public injection API. Check the same deadline reaches
|
||||
preparation, validation, and generation; do not add a new public testing seam.
|
||||
3. Test that notification time consumes the same budget and that expiry there
|
||||
prevents generation. Cover an earlier parent deadline and parent cancellation
|
||||
separately from a provider's own deadline. Preserve original injected error
|
||||
identities and do not relabel a non-context error after timer expiry.
|
||||
4. On both ordinary and split public execution, exercise a terminal observer
|
||||
that outlasts the operation budget after successful completion. The result
|
||||
stays successful and the terminal remains successful. Include the timeout
|
||||
failure case to ensure public error mapping happens before terminal delivery.
|
||||
5. After expiry, prove capacity remains usable and the caller parent stays
|
||||
active. Respect the current capacity model: logical admission may reject
|
||||
immediately, while admitted work can wait for an active generation permit.
|
||||
Do not introduce a new blocking admission queue to satisfy a test label.
|
||||
|
||||
Use channels for ordering and `testing/synctest` for controlled elapsed-time
|
||||
scenarios where its bubble rules apply. This repository's Go minimum supports
|
||||
it. Prefer in-memory fixtures and controlled transports; avoid real short sleeps
|
||||
or close-to-deadline assertions. Reuse the existing generation tests for retry
|
||||
policy rather than building a second retry matrix. There is no production clock
|
||||
framework, live provider probe, allocation threshold, or performance gate here.
|
||||
|
||||
Validation: run focused use-case/generation tests and the new public execution
|
||||
control tests under the race detector. The new cases should protect deadline
|
||||
propagation and classification, not private helper call sequences.
|
||||
|
||||
## Stage 6: Verify Notification Ownership And Failure Lifecycles
|
||||
|
||||
Outcome: applications can safely retain diagnostic details without altering
|
||||
execution or acquiring new lifecycle guarantees.
|
||||
|
||||
1. Add a representative continuation request containing history, follow-up
|
||||
messages, appended cache-control metadata, input hashes, session, settings
|
||||
with nested provider values, and a structured schema. Inside `OnPrepared`,
|
||||
retain and mutate the delivered mutable values; the model request, captured
|
||||
exchange, and later prepared-handle `Details()` remain unchanged. Use
|
||||
synthetic direct/environment credentials and verify their values are absent
|
||||
from diagnostic details while the existing client credential path still works.
|
||||
2. Demonstrate snapshot fidelity when mutable input/schema sources change after
|
||||
preparation and before execution. Reuse existing frozen-preparation fixtures;
|
||||
notification must describe the executed snapshot, not reread the changed
|
||||
sources. A later provider failure or cancellation may return no result, while
|
||||
the application still retains the delivered details.
|
||||
3. Verify absence of notification for preparation failure and ordinary admission
|
||||
rejection, without requiring extra reads to produce diagnostics. For split
|
||||
execution cover invalid/foreign/discarded/reused handles and pre-notification
|
||||
cancellation. `Details()`, `Prepare`, `ValidateRequest`, and preparation of an
|
||||
executable handle never notify or start this execution timer.
|
||||
4. Verify that retries and structural repair do not repeat notification. Reuse
|
||||
an existing retry-plus-repair integration scenario with an added notification
|
||||
assertion rather than duplicating its full event/usage test elsewhere.
|
||||
5. Recover a notification panic only in test code, then verify ordinary capacity
|
||||
is reusable and a claimed handle stays consumed. Do not require a terminal
|
||||
event after panic or impose a prohibition on callback reentrancy. A capacity
|
||||
one probe documents held admission rather than promising nested success.
|
||||
|
||||
Validation: run affected public contract and private payload-cleanup tests under
|
||||
the race detector. Mutable callback state in concurrent tests must be protected
|
||||
by the test; do not make PromptKit serialize application callbacks globally.
|
||||
|
||||
## Stage 7: Verify Coordinated Turns And Observer Composition
|
||||
|
||||
Outcome: coordination obtains the controls through ordinary `Run`, retaining
|
||||
its existing branching and delivery semantics.
|
||||
|
||||
1. Check the coordinator's existing request-value copy preserves both new
|
||||
controls while it replaces `ContinueFrom` and composes observers. No separate
|
||||
coordinator timeout, executor, or public prepare/run sequence is needed.
|
||||
2. Add a controlled-time, two-continuation success case. Each turn finishes
|
||||
within its own timeout while their combined execution exceeds one turn's
|
||||
duration. Callback details contain each turn's assembled history; no timer
|
||||
from an earlier turn controls a later turn.
|
||||
3. In the next-turn callback, verify the parent context is active and the prior
|
||||
child context has been cleaned up. Run an explicitly selected assessment on
|
||||
the same backend with concurrency one and queue capacity zero, using its own
|
||||
timeout. This differs from `OnPrepared`, where admission is still held.
|
||||
4. Exercise a locally timed-out continuation: coordination returns its ordinary
|
||||
operational error with the marker, does not fabricate an outcome or completed
|
||||
exchange, and leaves the parent and a sibling continuation usable. Retained
|
||||
details are available if notification occurred before failure. Do not promise
|
||||
them if execution stopped earlier.
|
||||
5. Compose request and coordinator observers with an explicit execution group.
|
||||
Check one ordinary lifecycle per selected run, normal terminal usage/attempt
|
||||
totals, and no implicit membership for assessment calls. Reuse existing
|
||||
final-turn and parent-cancellation/undelivered-result cases to verify that
|
||||
cleanup and slow terminal observation have not changed delivery semantics.
|
||||
|
||||
Validation: run the coordinator, observation, group, and new execution-control
|
||||
contract cases together under the race detector. Keep tests at the public
|
||||
boundary for the assembled behavior; the internal coordinator loop need not
|
||||
be redesigned solely because its ordinary run gained options.
|
||||
|
||||
## Stage 8: Document, Demonstrate, And Validate The Assembled Feature
|
||||
|
||||
Outcome: the implementation and its supported consumer workflow are complete,
|
||||
with documentation in the canonical owners.
|
||||
|
||||
1. Finish GoDoc on `RunRequest`, `ErrOperationTimeout`, `Run`, `Prepare`,
|
||||
`ValidateRequest`, `PrepareExecution`, `RunPrepared`, and `PreparedExecution`.
|
||||
Cross-reference the owning field/error contract rather than duplicating its
|
||||
entire definition. Explain conditional notification, held admission,
|
||||
cooperative cancellation, split preparation, callback ownership, and outcome
|
||||
finalization before terminal observation.
|
||||
2. Update the [consumer guide](../consumers/pkg-promptkit.md) with small ordinary,
|
||||
coordinated, and split usage sketches linked to GoDoc. Show a caller-owned
|
||||
retained `PreparedRun` on failure, `errors.Is` checks for both timeout
|
||||
identities, and a separate budget for callback-owned assessment. Do not add
|
||||
persistence, log destinations, redaction policy, or a mandatory diagnostic
|
||||
write gate.
|
||||
3. Extend the maintained [observation example](../../examples/go-library/observe/main.go)
|
||||
and its semantic test with a positive operation budget on continuation,
|
||||
selected prepared-details retention, and a separately budgeted next-turn
|
||||
assessment. Keep it offline, synthetic, and successful; Stage 5/6 tests own
|
||||
failure demonstrations. Do not add another standalone example framework.
|
||||
4. Update [runner documentation](../internal/runner.md),
|
||||
[observation documentation](../internal/observation.md), and the
|
||||
[component inventory](../internal/overview.md) only where responsibilities or
|
||||
lifecycle descriptions changed. No ConfigKit, collection-format, provider
|
||||
payload, or architectural policy change is required by this work.
|
||||
5. Review Audita's six acceptance scenarios and the feature roadmap's validation
|
||||
targets against the completed tests. Consolidate duplicate tests; do not
|
||||
expand this into a full cross-product of all entry points, phases, observers,
|
||||
and callback behaviors. Retain existing no-option regression coverage.
|
||||
6. Select the newest installed Go toolchain per the development guide. Format
|
||||
changed Go files, run `go test -race ./...` and `go vet ./...` with
|
||||
`GOTOOLCHAIN=local` and `GOWORK=off`, and run `git diff --check`. The full Go
|
||||
suite includes the maintained examples; no second example execution gate is
|
||||
needed. Use writable caches as required by the development environment.
|
||||
Validate local links and inspect the full diff for unintended files/secrets.
|
||||
|
||||
Do not edit published v0.22.0 release notes, create a new release/tag, or require
|
||||
CI or external publication to finish the sprint. Release preparation and
|
||||
retirement of these roadmaps are subsequent work.
|
||||
|
||||
## Completion Criteria
|
||||
|
||||
- Ordinary and coordinated runs apply one optional whole-operation budget;
|
||||
split handles retain duration and callback selection without live idle timers.
|
||||
- Deadline attribution survives public wrapping, distinguishes this scope's
|
||||
recorded timer cause, and agrees with terminal observation before cleanup.
|
||||
- Notification supplies a detached redacted view of the actual logical prepared
|
||||
request, once before generation when reached, without repeated preparation.
|
||||
- Failure, cancellation, and panic paths preserve existing resource, handle,
|
||||
error, observation, grouping, and continuation behavior.
|
||||
- The maintained example, canonical documentation, focused tests, full race
|
||||
suite, and vet are complete. No-option use stays compatible.
|
||||
|
||||
No significant open questions remain. The API and nonpositive-duration choices
|
||||
above complete the planning decisions left by the accepted feature roadmap.
|
||||