Plan the remaining audit remediation work
This commit is contained in:
@@ -2,19 +2,19 @@
|
||||
|
||||
## Status, Purpose, And Ownership
|
||||
|
||||
**Status:** Target design and scope accepted; detailed implementation planning
|
||||
and implementation pending.
|
||||
**Status:** Target design and scope accepted; the staged
|
||||
[implementation plan](implementation.md) is prepared. Implementation is pending.
|
||||
|
||||
This roadmap defines the end state and required work for the remaining
|
||||
[audit catalog](audit/catalog.md) findings, incorporating the accepted decisions
|
||||
in the [discussion record](audit/discussion.md). It is the feature/design handoff
|
||||
to a planning agent, not the worker's detailed execution plan. No application
|
||||
to an implementation agent, not the worker's detailed execution plan. No application
|
||||
changes are implemented by this document.
|
||||
|
||||
The catalog owns finding inventory, evidence links, and implementation status.
|
||||
The discussion preserves decision rationale. This roadmap owns the consolidated
|
||||
target and scope; a subsequent implementation plan will own ordered worker
|
||||
stages, concrete dependencies, verification, and progress. Original audit reports
|
||||
target and scope; the implementation plan owns ordered worker stages, concrete
|
||||
dependencies, verification, and progress. Original audit reports
|
||||
describe their historical baseline and are not instructions to restore superseded
|
||||
behavior, particularly diagnostic group caps.
|
||||
|
||||
@@ -319,33 +319,17 @@ name-length cap, or new benchmark gate is part of acceptance. Future email/NWS
|
||||
integrations, broader domain/package migration, release publication, and upstream
|
||||
feature work are outside this remediation.
|
||||
|
||||
## Planning Handoff And Sequencing
|
||||
## Implementation Handoff
|
||||
|
||||
Prepare one detailed implementation plan for a worker to execute in order. Keep
|
||||
the completed core migration's plan/history intact. Use this roadmap as the target;
|
||||
the planner selects concrete Go signatures, files, and independently reviewable
|
||||
stages, without reopening accepted policy choices or treating historical audit
|
||||
recommendations as stronger authority than the decisions here.
|
||||
The [implementation plan](implementation.md) owns ordered worker stages, concrete
|
||||
APIs, dependencies, checks, and progress. The completed core migration is the
|
||||
baseline; its former detailed plan remains available in Git history. Accepted
|
||||
decisions here qualify historical audit recommendations. A new conflict with the
|
||||
target must be reported rather than silently changing inputs, acceptance, or scope.
|
||||
|
||||
Recommended ordering is narrow correctness fixes, ordinary-run source efficiency,
|
||||
capture ownership/representation, finalization and shutdown, composition/domain
|
||||
helpers, and remaining cleanup/final acceptance. This is dependency guidance, not
|
||||
an artificial serial dependency between independent fixes. Improve fragile tests
|
||||
before relying on them, and update interface documentation with affected changes.
|
||||
Keep package extraction distinguishable from evidence behavior changes and narrow
|
||||
bug fixes distinguishable from readability refactors.
|
||||
|
||||
For each worker stage, identify the catalog coverage, scope, prerequisites,
|
||||
observable completion criteria, relevant validation, and documentation updates.
|
||||
Verify current callers and partial fixes before prescribing changes. Ensure no
|
||||
required finding disappears inside a broad refactor and no resolved finding becomes
|
||||
a second migration. Report any newly discovered conflict rather than silently
|
||||
strengthening inputs, acceptance, or compatibility requirements.
|
||||
|
||||
The planner should specify a usable intermediate state and focused commits. Detailed
|
||||
test commands and exact stage boundaries belong in that plan; no new framework or
|
||||
mandatory test matrix is needed to express them. Handing off or executing that plan
|
||||
is subsequent work, not part of creating this roadmap.
|
||||
Implementation is one end-to-end sprint; intermediate buildability is not a
|
||||
separate product requirement. Completion is judged against the target below,
|
||||
not an intermediate compatibility surface or a closed-finding count.
|
||||
|
||||
## Verification And Completion
|
||||
|
||||
@@ -374,5 +358,5 @@ what was actually resolved; CAT-033 remains deferred. Canonical documentation,
|
||||
implementation status, and code must agree. A smaller file, green happy-path test,
|
||||
or closed finding count alone is not evidence of completion.
|
||||
|
||||
There are no unresolved product or scope decisions. Remaining API details and
|
||||
stage decomposition are implementation planning choices within these boundaries.
|
||||
There are no unresolved product or scope decisions. The implementation plan
|
||||
records selected APIs and stage decomposition within these boundaries.
|
||||
|
||||